Installation
CWS
−
D100
−
B Welding System
2005 Swagelok Company, All right reserved
September 2005
2-10
Installing the Typical Shielding/Purge
Gas Delivery System
Install the Shielding/Purge Gas Delivery System. Figure 2-6
shows a typical system. Be sure to adhere to the
following precautions:
D
Ensure that the gas storage container(s) are secured
before using them.
D
Ensure all connections are tight and do not leak.
D
Use only a Swagelok single-ended shut-off
Quick-Connect stem on the shield/purge line
for the shielding gas connector.
D
Adjust the low-pressure regulator gage to reduce
the gas storage container source pressure to 25 psig
to 50 psig.
When complete, continue to the
Preliminary Check
procedure beginning on page 2-14.