Installation Instruction
16 Modular UPS 25KVA~900KVA User Manual
Fig.3-4 Remove the protective foam
5.
Check the UPS.
(a) Visually examine if there are any damages to UPS during transportation. If
any, contact to the carrier.
(b) Check the UPS with the list of the goods. If any items are not included in the
list, contact to our company or the local office.
6.
Dismantle the bolt that connects the cabinet and wooden pallet after disassembly.
7.
Move the cabinet to the installation position.
Attention
Be careful while removing to avoid scratching the equipment.
3.2.2 Unpacking Power Module
1.
The steps to move and unpack the power module are as follows
:
2.
The packing case must be placed on the platform smoothly, as is shown in
Fig.3-5.
Fig.3-5 Place on
platform
smoothly
3.
Cut the plastic packing belt and scotch tape to open the carton.
see Fig.3-6
)
.