Conversion from natural gas to propane
Conversion of the boiler to a different gas type must be performed by a certified technician.
Parameter 138 must be set correctly!
Wrong setting can lead to damage to the appliance or shorten the lifespan of the appliance!
The warranty of the device will expire if a wrong selection has been made.
Use only parts/conversion kits obtained from Slant Fin and
intended to be used with this particular boiler. Every
conversion kit is provided with instructions how to
assemble the kit to the boiler.
Converting the boiler to propane (LP) requires the following actions (details below).
1. check boiler model
2. check burner controller type
3. mount
the
orifice
4. set
parameter
138
5. adjust
the
CO
2
/ O
2
percentage
6. confirmation: apply the propane sticker and mark the boxes
1. Check
boiler
model.
Check if you have a 299, 399 or 500 boiler. The model number is on the dataplate, on
the inside of the boiler casing, top side.
2. Check burner controller type.
Check which controller type is installed, see picture.
- if a model number is on the sticker on the controller,
the boiler is equiped with an internal igniter.
- if a sticker "EXTERNAL IGNITER 299/399/500 MBH"
is present on the controller, the boiler is equiped
with an external igniter.
3. Mount
the
orifice:
Converting the boiler to propane is done by placing a propane
orifice between gas valve and venturi. By using the correct orifice
size (see table), the measured CO
2
(O
2
) percentage in the flue
gas will already be close to the desired value.
Installing the orifice (see also picture):
Required tools: wrench 55, hex key 5 mm and hex key 4 mm.
1. Close the external gas shutoff valve and disconnect the
electrical power before opening the boiler.
2. Use a wrench to open the coupling in the gas line in the boiler.
The three screws, with which the venturi is mounted onto the
fan, can now be removed.
3. Venturi and gas combination valve can now be separated. The
orifice is to be placed between venturi and gas combination
valve. The rounded side of the orifice must be on the side of
the gas combination valve.
The orifice must be mounted into the gas entrance of the
venturi and secured with the rubber gasket.
4. Venturi and gas combination valve can now be reconnected.
5. Remount the gas combination valve and the venturi onto the
fan. Close the union in the internal gas line.
6. Now open the external gas valve.
7. Check for gas leaks.
8. Reconnect the electrical power.
9. If in operation, check again for gas leaks on all parts that have
been apart.
Required parts:
(see § 5.1 Accessories)
Propane kit for VMS Venturi hole Ø 6.2 VGH 299
Propane kit for VMS Venturi hole Ø 6.7 VGH 399
Propane kit for VMS Venturi hole Ø 7.2 VGH 500
Picture 18. 4
Boiler type
Orifice Inner Diameter
VGH 299 CH
6.2
VGH 399 CH
6.7
VGH 500 CH
7.2
Table 18. 2
Picture 18. 5
WARNING
Orifice
Gasket
Sticker
EXTERNAL IGNITER
299/399/500 MBH
299MBH VERSION
399MBH VERSION
500MBH VERSION
Summary of Contents for VGH-299-CH
Page 6: ...E93 1601EN032 C VGH installation manual 6 1 SAFETY GUIDELINES ...
Page 59: ...E93 1601EN032 C VGH installation manual 59 Ladder Logic Diagram Figure 11 3 ...
Page 60: ...E93 1601EN032 C VGH installation manual 60 Electrical schematics Figure 11 4 ...
Page 61: ...E93 1601EN032 C VGH installation manual 61 Figure 11 5 ...
Page 123: ...E93 1601EN032 C VGH installation manual 123 22 SPARE PARTS Figure 22 1 ...
Page 124: ...E93 1601EN032 C VGH installation manual 124 Figure 22 2 ...
Page 127: ...E93 1601EN032 C VGH installation manual 127 ...