Advanced commissioning
7.3 Setpoints
Converter with control units CU250D-2
Operating Instructions, 04/2015, FW V4.7.3, A5E34261542B AB
127
7.3.2
Specifying the setpoint via the fieldbus
Interconnecting the fieldbus with the main setpoint
Figure 7-8
Fieldbus as setpoint source
Most standard telegrams receive the speed setpoint as a second process data PZD2.
Table 7- 3
Setting the fieldbus as setpoint source
Parameter
Remark
p1070 = 2050[1]
Main setpoint
Interconnect the main setpoint with process data PZD2 from the fieldbus.
p1075 = 2050[1]
Additional setpoint
Interconnect the additional setpoint with process data PZD2 from the fieldbus.