6
COMMISSIONING AND CONFIGURATION
66
8011325/18IM/2020-07-02|SICK
O P E R A T I N G I N S T R U C T I O N S | ICR880/890
Subject to change without notice
6
Commissioning and configuration
Commissioning of the camera systems and diagnostics during operation are carried out
using the SOPAS-ET configuration software.
WARNING
Do not commission without testing by qualified safety personnel
Before you commission the Asset Monitoring System for the first time, you must have it
checked and approved by qualified safety personnel.
▸
Observe the notes provided in chapter
NOTE
Do not switch off the voltage supply during the configuration!
If you switch off the voltage supply during the configuration, you will lose all parameters
that have already been configured.
6.1
Starting up the camera system
The camera system does not have an external power switch. The controller unit supplies
it with power.
▸
Connect the voltage supply via the controller unit.
The camera systems connected to the controller unit are started up and checked for
operational readiness in a self-test.
The
Device Ready
LED on the camera system lights up green after the self-test.
Fig. 46: Checking the operational readiness