TECHNICAL BULLETIN:
A06/07 FEAC WATER SUPPLY REQUIREMENTS
In order to avoid unnecessary inconvenience
to our Consumers, we would like to
reinforce Seeley Internationals Water supply
requirements outlined in our FEAC Coolers
(Breezair, Braemar, Convair & Coolair)
Installation Manuals.
WATER REQUIREMENTS
Installation of the Cooler water supply must
conform to local plumbing rules, regulations
and standards.
The following points and specifications for
water supply must be adhered to:
•
Water Connection: ½” inch BSP
•
Water Supply: 800Kpa (115 psi)
MAXIMUM
Important!
If the water pressure exceeds
this maximum specification then a pressure
reducing valve is required and must be
supplied and fitted by the installer.
•
Install a manual shut off valve in the
water supply line adjacent to the Cooler
subject to local plumbing regulations. It
is
recommended
to use
a ¼ turn ball
type shut off valve.
This allows the
water supply to be isolated whenever
work needs to be done on the Cooler.
It
is recommended to use a stopcock,
i.e.
NOT a non-return type of shut off valve.
•
Flush the water pipe to remove any swarf
(debris) before final fitting.
•
In areas subject to freezing, the water line
needs a drain down facility. This is when
water can be drained from the Coolers
water supply pipes during the winter
periods to eliminate the risk of bursting
pipes caused by the expansion of frozen
water.
X
Incorrect
Correct
Subject: FEAC Water Supply Requirements
Bulletin Number: A06/07
Region: Australia
Author: Technical Support 1300 650 399
Date: 24/09/2007
TECHNICAL BULLETIN
Important! Consequential damages for
installations that do not comply with these
requirements will not be accepted by
Seeley International
.