Rockwell Automation Publication 1734-UM013J-EN-P - July 2014
149
Replacing POINT Guard I/O Modules
Chapter 8
If you download this configuration to a temporary setup, place the module
on the network and it automatically connects to the controller.
If the configuration downloaded to the module was not from the original
DNT file, the configuration signature will not match the original. Even if
you recreate the same parameters in a new DNT file, the time and date
portions of the signature will be different so the connection to the
controller is not made. If this occurs, click the Safety Connection tab for
the controller that prompted you that the configuration signature is
different and provides you with the option to match the new configuration
signature. However, you should first re-validate the safety system because it
is not using the original DNT file.
7.
Click Yes.
This takes the controller out of Run mode and prompts you to download
the changes.
8.
Click Yes to download the new connection configuration to the
SmartGuard controller.
After the download is complete, place the controller back in Run mode
and the connection to the replacement module is established.
9.
Follow your company-prescribed procedures to functionally test the
replaced I/O module and system and to authorize the system for use.
Summary of Contents for Allen-Bradley 1734-IB8S
Page 1: ...POINT Guard I O Safety Modules Catalog Numbers 1734 IB8S 1734 OB8S 1734 IE4S User Manual ...
Page 4: ...4 Rockwell Automation Publication 1734 UM013J EN P July 2014 Summary of Changes Notes ...
Page 10: ...10 Rockwell Automation Publication 1734 UM013J EN P July 2014 Table of Contents ...
Page 14: ...14 Rockwell Automation Publication 1734 UM013J EN P July 2014 Preface Notes ...
Page 186: ...186 Rockwell Automation Publication 1734 UM013J EN P July 2014 Appendix D Safety Data Notes ...
Page 211: ......