General instructions
cpg
.0 lite: GIS medium-voltage switchgear,
gas insulated, up to 24 kV,
in accordance with IEC Standard
Operations sequence
d.
Remove the operating lever. The selector switch
automatically returns to its central position.
Figure 7.118.
Final position after completing the operation
3.
Open the top earthing switch.
a.
Move its selector switch to the right, to earthing
switch position.
Figure 7.119.
Selector switch in earthing switch position
b.
Insert the earthing switch operating lever (YELLOW
knobs) in the actuating shaft of the top earthing
switch (area marked with YELLOW line).
Figure 7.120.
Lever inserted in the top earthing switch actuating shaft