Operations sequence
7.3.6. Left busbar earthing opening operation
Starting position:
circuit-breaker CLOSED, spring
charging status indicator shows UNCHARGED,
top feeder disconnector OPEN, bottom feeder
disconnector CLOSED, top earthing switch CLOSED,
and bottom earthing switch OPEN.
Check that the SF
6
level is correct before starting the
operation
1.
Open the circuit-breaker. Press the "O" pushbutton. The
circuit-breaker status indicator shows OPEN.
Figure 7.114.
Circuit-breaker open
2.
Open the bottom feeder disconnector.
a.
Move its selector switch to the right, to feeder
disconnector position.
Figure 7.115.
Selector switch in feeder disconnector position