Operations sequence
General instructions
cpg
.0 lite: GIS medium-voltage switchgear,
gas insulated, up to 24 kV,
in accordance with IEC Standard
3.
Insert the feeder disconnector operating lever (BLACK
knobs) in the feeder disconnector actuating shaft (area
marked with WHITE line).
Figure 7.40.
Lever inserted in the feeder disconnector actuating shaft
4.
Turn the lever ANTICLOCKWISE until final actuator
position is reached.
Figure 7.41.
Feeder disconnector open, after turning the lever
5.
Remove the operating lever. The selector switch
automatically returns to its central position.
Figure 7.42.
Final position after completing the operation