Operations sequence
General instructions
cpg
.0 lite: GIS medium-voltage switchgear,
gas insulated, up to 24 kV,
in accordance with IEC Standard
Disconnection
Check that the SF
6
level is correct before starting the
operation
1.
Move the selector switch to the left, to feeder
disconnector position.
Figure 7.6.
Selector switch in feeder disconnector position
2.
Insert the feeder disconnector operating lever (BLACK
knobs) in the feeder disconnector actuating shaft (area
marked with WHITE line).
Figure 7.7.
Lever inserted in the feeder disconnector actuating shaft