IG-310-EN version 01; 31/03/2021
38
Operations sequence
General instructions
cpg
.0 lite: GIS medium-voltage switchgear,
gas insulated, up to 24 kV,
in accordance with IEC Standard
c.
Turn the lever ANTICLOCKWISE until final actuator
position is reached.
Figure 7.28.
Earthing switch open, after turning the lever
d.
Remove the operating lever. The selector switch
automatically returns to its central position.
Figure 7.29.
Final position after completing the operation
7.
Perform the dielectric tests on the cables.
8.
Operate in reverse direction to return to the initial state:
a.
Close the earthing switch
b.
Remove the test tools
c.
Place the internal arc protection kit in the cable
compartment and the cable compartment cover
d.
Open the earthing switch