48
www.climacoolcorp.com
All startups must be performed by ClimaCool factory
trained personnel .
1 .
Review all items are complete from the Pre-Startup
Checklist .
2 .
Cross reference model number with submittal sheet
to verify that the units are the correct model type and
voltage requirements .
3 .
Verify the location and wiring connections of all main
header temperature sensors (should be a minimum of
36” but no more than 60” from the bank). Confirm that
all sensors are FULLY INSERTED into their sensor wells
and wired back to the correct terminals in the Master
Control Panel .
4 .
Verify the location and ports for all water differential
pressure sensors used for flow detection ((+) port piped
to the inlet headers and the (-) ports piped to the outlet
headers) .
• Verify the correct wiring using the +5VDC power
supply to the differential sensor inputs.
• Verify the correct output wiring from the
differential sensors back to the master controller
universal input (UI) channels 8 and 11. Confirm
inputs 8 & 11 jumpers are set for ‘volts’ . Note: The
differential sensor ports should NOT be piped to a
location which includes strainer pressure drops .
5 .
Verify that strainer inlet includes a strainer assembly
equipped with a 60 mesh screen .
6 .
Inspect all refrigerant piping for oil leaks which may
have occurred during shipment which might indicate a
refrigerant leak . Check the high pressure cutout setting
of the pressure controls . The setting should be 385 psig
cutout for all UCR models .
7 .
Verify the location and settings of the phase loss
monitor . It should be in a location to sense the voltage
condition in the main, high voltage panel which feeds
high voltage to each module independently (review
Electrical Connection on page 15) . Verify the low voltage
output wiring from the phase loss monitor (terminals
4 and 5) back to the main CoolLogic controller, input
channel 12 .
8 .
Determine if the chiller modules are equipped with
motorized water isolation valves . If so, verify the
settings of the motorized valves auxiliary switch dial
settings, to ensure they close near:
• 15% for load side (evaporator or heat) .
9 .
Confirm that the main water pumps are driven by VFD’s,
and that all VFD’s are controlling the pump speeds to
produce a nominal differential pressure drop across
the chiller bank headers, measured precisely at the
differential pressure sensor locations in step 4 above.
Nominal differential pressure ranges are from 3 to
10 psid .
10 .
Confirm the jumper locations for all master controller
and module controllers as shown on the wiring
diagrams provided on the inside electrical door panels .
• Set the rotary switches for the MAC Address of the
master controller to be “01 .”
• Set the rotary switches for the module controllers
to be “02” for module #1, “03” for module #2, and
so on .
11 .
Tighten every screw and lug connection inside the
CoolLogic master control panel and inside each module
control panel high voltage section . Check auxiliary
contacts on contactors ensure #1 auxiliary is wired on
the #1 contactor . Open up the compressor junction box
located on the front of each compressor and verify main
electrical terminal lug tightness and the low voltage
wires on protection module .
12 .
Verify the communication cable wiring to ensure it
is 22 AWG, simple two conductor shielded cable and
that the wiring is alone inside solid conduit between
the master control panel and the first module control
panel . Verify the cable’s outer jacket is not stripped
more than one inch . If so, the wires may have become
untwisted, causing signal reflections. Confirm the wires
are connected correctly to the terminal blocks at the
master and each module as follows:
Black wire to Net-
White wire to Net +
Shield wire to Shield
Verify that the shield part of the wires continues the
daisy chain connection through to the last module but,
that this shield is NOT connected to a terminal lug inside
any module .
13 .
Power-up the master control panel and download the
appropriate clipping file into the master controller,
following instructions .
14 .
Power up each module control panel, turn OFF the two
toggle switches located on the inside bottom of the low
voltage side of the module electrical panel . Download
the appropriate clipping file into the module controllers,
following instructions .
15 .
Check for proper line or high voltage values at each
module input power block, and the 24 VAC low voltage
values for correctness (+/- 10% of nominal values) .
16 .
On 208/230V units, confirm transformer(s) are properly
tapped for the measured incoming power supply .
17 .
Use refrigerant gauge set suitable for the high pressure
R-410A, and hook up to the suction and discharge
ports of each module’s compressor stages separately .
Bump start the compressors either by depressing
the contactor manually, or by using the manual run
commands from the Master Control Panel, (found in
the FN 7, or the service menu) . Bump the compressor
only for 1-2 seconds to ensure the correct rotation of
the scroll compressors (indicated by a rising highside
pressure and a falling suction pressure) .
Startup
Summary of Contents for CLIMACOOL UCR 30
Page 19: ...17 www climacoolcorp com Voltage Phase Monitor Wiring Diagram...
Page 29: ...27 www climacoolcorp com Evaporator Water Pressure Drop Charts...
Page 30: ...28 www climacoolcorp com Glycol Performance Adjustments Factor Charts...
Page 78: ...76 www climacoolcorp com Wiring Diagram...
Page 79: ...77 www climacoolcorp com Wiring Diagram...
Page 80: ...78 www climacoolcorp com Wiring Diagram CoolLogic Control Panel...
Page 81: ...79 www climacoolcorp com Wiring Diagram CoolLogic Control Panel...