- 36 -
8.1
On-site adjustment flowchart
When BAC-HD150 is connected to PAC-YG50ECA, on-site adjustment is divided into two steps as follows.
Before following the steps below, set the M-NET address, group, and interlocked operation with LOSSNAY for PAC-YG50ECA
by using AG-150A, and complete a test run for the air conditioning units.
By following these steps, the cause of trouble can be solved clearly and on-site adjustment can be identified efficiently.
It is recommended to follow the steps below.
8 On-site adjustment steps (When BAC-HD150 is connected to PAC-YG50ECA)
Step - 1 Initial settings for the BAC-HD150 system and BACnet
®
related items
Make the setting for the BAC-HD150 system and BACnet
®
related items by using Setting
Tool.
(Refer to the Instruction Book that came with Setting Tool for BAC-HD150 system setting
and setting related to BACnet
®
.)
Step - 2 Test run of BAC-HD150
Check that operation status of conditioning units appears correctly on the BMS and that air
conditioning units operate properly from the BMS control.
WT05542X04.book Page 36 Wednesday, July 3, 2013 12:13 PM