- 30 -
7.1
On-site adjustment flowchart
When BAC-HD150 is connected to M-NET, on-site adjustment is divided into four steps as follows. By following these steps,
the cause of trouble can be solved clearly and on-site adjustment can be identified efficiently.
It is recommended to follow the steps below.
7 On-site adjustment steps (When BAC-HD150 is connected to M-NET)
Step - 1 Initial setting for air conditioning system
Make the setting for the BAC-HD150 system and air conditioning system group by using
Setting Tool.
Refer to the Instruction Book that came with the Setting Tool for BAC-HD150 system setting
and group setting for air conditioning system.
Step - 2 Test run of air conditioning system
Check that air conditioning units and controllers are system configured correctly and
operate properly. (Refer to the Installation Manual that came with each device for how to
perform test run.)
Step - 3 Initial settings for BACnet
®
related items
Make the setting for the BACnet
®
related items by using Setting Tool.
Refer to the Instruction Book that came with Setting Tool for setting related to BACnet
®
.
Step - 4 Test run of BAC-HD150
Check that operation status of air conditioning units appears correctly on the BMS and that
air conditioning units operate properly from the BMS control.
BMS: Building Management System
WT05542X04.book Page 30 Wednesday, July 3, 2013 12:13 PM