RECEIPT OF GOODS AND STORAGE
The gas sample probe and any special accessories should be removed carefully from the packaging and checked
immediately for completeness against the delivery note.
Check the goods for any damage incurred during transport and if necessary inform your transport insurer of any
damage.
The gas sample probe is normally delivered in two packaging units:
1.
The gas sample probe with the screws, nuts and flange seal required for mounting.
2.
Sample tube or prefilter, if applicable with extension tube.
Note
The equipment should be stored in a protected, frost-free room!
13
PREPARATION FOR INSTALLATION
Select the optimal sampling point in accordance with the generally applicable guidelines or consult the com-
petent persons.
Locate the sampling point in such a way that there is adequate space for inserting and removing the probe and
pay attention to the insertion length of the probe tube.
Make certain that the probe is easily accessible so that you can carry out any subsequent maintenance work
without trouble.
Locate the probe connections in such a way that the connections' temperature is always above the acid dew
point in order to avoid corrosion and blockage problems. If this is not possible, a heated
SP35/SP30
probe tube
is recommended for cold connections.
If the ambient temperature in the area of the connections is > 80 °C [176 °F] as a result of radiated heat, then a
radiated-heat deflector must be mounted to protect the probe.
The connection's mounting flange connection should comply with DN65 PN6. If other connection sizes are
required, a special adapter flange
/S010
can be supplied as an option. Instead of flange connection mounting,
the probe can also be mounted using a
/SO1
R2" adapter on a corresponding threaded sleeve connection. This
adapter can be supplied. The necessary minimum flange size and the minimum connection diameter depends
on the diameter of the probe tube or prefilter used.
Summary of Contents for SP Series
Page 48: ...48 SP2000 SP2300 SP2400 1 00 03 www mc techgroup com Figure 24 SP2000 H basic version ...
Page 49: ...www mc techgroup com SP2000 SP2300 SP2400 1 00 03 49 Figure 25 SP2000 H with options ...
Page 50: ...50 SP2000 SP2300 SP2400 1 00 03 www mc techgroup com Figure 26 SP2300 H ...
Page 51: ...www mc techgroup com SP2000 SP2300 SP2400 1 00 03 51 Figure 27 SP2300 H filter elements ...
Page 53: ...www mc techgroup com SP2000 SP2300 SP2400 1 00 03 53 Figure 29 Heated sample tubes SP30 H ...
Page 54: ...54 SP2000 SP2300 SP2400 1 00 03 www mc techgroup com ...
Page 56: ...56 SP2000 SP2300 SP2400 1 00 03 www mc techgroup com Figure 31 SP2000 H 3VA MS NC B ...
Page 57: ...www mc techgroup com SP2000 SP2300 SP2400 1 00 03 57 Figure 32 SP2000 H 3VA MS NC C ...
Page 58: ...58 SP2000 SP2300 SP2400 1 00 03 www mc techgroup com Figure 33 SP2000 H 3VA MS NO B ...
Page 59: ...www mc techgroup com SP2000 SP2300 SP2400 1 00 03 59 Figure 34 SP2000 H 3VA MS NO C ...