7. First start-up
To ensure safety and functionality, the person specified by the operator is required to perform the following inspections. Any detected
deficiencies must be remedied prior to initial start-up. The correction of deficiencies must be done exclusively by a specialist competent
and authorized to do so.
7.1 Inspections before first start-up
Table 39
Mark the following with: Yes
or
No
Series SMBM
Product variant:
Yes No
If present, electrical connection of the pulse generator 2340-00000091 is executed correctly
If present, electrical connection of the signal transmitter 24-1072-2125 is executed correctly
If present, electrical connection of the 3/2 changeover valve 24-1254-3437 is executed correctly
Equipotential bonding fully present, properly connected, and electrically continuous
The performance characteristics for the aforementioned connections match the specifications in "Technical data"
Mechanical connection established correctly
All components such as lubrication piping are correctly mounted
No apparent damage, contamination, or corrosion
Any dismantled protective and monitoring equipment (of the main machine) is fully reinstalled and functional
No dust accumulations present
7.2 Inspections during first start-up
Table 40
Mark the following with: Yes
or
No
Series SMBM
Product variant:
Yes No
Unusual noises, vibrations
Undesired discharge of lubricant at connections
Impurities in the lubricant
Lubricant is fed without bubbles.
The bearings/friction points requiring lubrication receive the planned lubricant volume