3
INSTALLATION
14
OPTISONIC 6400
www.krohne.com
08/2011 - 4000972602 - MA OPTISONIC 6400 R02 en
3.2.2 Long horizontal pipes
•
Install on slightly ascending pipe section.
•
If not possible, ensure adequate velocity to prevent air, gas or vapor from collecting in upper
part.
•
In partially filled pipes, the clamp-on flowmeter will report incorrect flow rates, or not
measure.
3.2.3 Vertical pipelines
Figure 3-2: Long horizontal pipes
CAUTION!
•
Ensure that the pipe is fully filled at all times.
•
Both ascending and descending flow direction is measurable.
•
Observe the required in- and outlets.
Figure 3-3: Mounting on vertical pipelines is possible