52
451253/A
3
Mount the unit to the bulkhead with M10 bolts. These bolts must be supplied by
the shipyard.
• As the Transceiver Unit is heavy, a lifting arrangement (articulated jack or
similar) must be used.
• The foundation onto which the Transceiver Unit is mounted will determine the
correct torque to be applied to the bolts. Use maximum torque 64 Nm.
4
Alternatively, the shock absorbers can be mounted to a pair of specially designed
support brackets.
Shown in
Figure 25 , 871–212984, page 124
Interconnection cables and interfaces
1
Prepare the support bracket to receive the transducer array cables on the lower
frame Refer to Interconnection cables support bracket for the cable entries.
The cabling layout and interconnections are described in Cable layout and
interconnections.
For more information, see:
Figure 27 , 448231_1A, page 126
2
Mount the cables according to the cable plan.
Make sure that the cable tables are filled in correctly.
Shown in
Table 13 CCU1 cable labelling, page 70
3
Close and secure support bracket to secure the cables.
4
Secure the interface cables by strapping them to the transducer cables.
Surface preservation
All metal surfaces which are likely to corrode should be painted. This includes welds,
base frames and support brackets. Make appropriate cautions to avoid spilling paint
on the cabinet.
Hydrographic Work Station
This section describes the installation of the SBP 29 Hydrographic Work Station in
the operation room.
Description
The SBP 29 has one Hydrographic Work Station.
Generally, this unit is a commercial work station. The Hydrographic Work Station
includes display monitor, keyboard and mouse or trackball.
SBP 29 Installation Manual
Summary of Contents for SBP 29
Page 1: ...451253 A November 2019 Kongsberg Maritime AS SBP 29 Sub bottom profiler Installation Manual ...
Page 111: ...451253 A 111 Figure 12 862 216859 Drawing files ...
Page 112: ...112 451253 A Figure 13 307904 SBP 29 Installation Manual ...
Page 113: ...451253 A 113 Figure 14 862 218001 Drawing files ...
Page 114: ...114 451253 A Figure 15 871 219193 SBP 29 Installation Manual ...
Page 115: ...451253 A 115 Figure 16 871 219201 Drawing files ...
Page 116: ...116 451253 A Figure 17 388168 SBP 29 Installation Manual ...
Page 117: ...451253 A 117 Figure 18 871 219187 Drawing files ...
Page 118: ...118 451253 A Figure 19 821 219199 SBP 29 Installation Manual ...
Page 119: ...451253 A 119 Figure 20 388235 Drawing files ...
Page 120: ...120 451253 A Figure 21 871 219198 SBP 29 Installation Manual ...
Page 121: ...451253 A 121 Figure 22 388148 Drawing files ...
Page 122: ...122 451253 A Figure 23 315550 SBP 29 Installation Manual ...
Page 123: ...451253 A 123 Figure 24 430751 Drawing files ...
Page 124: ...124 451253 A Figure 25 871 212984 SBP 29 Installation Manual ...
Page 125: ...451253 A 125 Figure 26 407070 Drawing files ...
Page 126: ...126 451253 A Figure 27 448231_1A SBP 29 Installation Manual ...
Page 127: ...451253 A 127 Figure 28 427512 Drawing files ...
Page 128: ...128 451253 A Figure 29 435680 SBP 29 Installation Manual ...
Page 129: ...451253 A 129 Figure 30 444783 Drawing files ...
Page 151: ......
Page 152: ... 2019 Kongsberg Maritime ...