The information here must be considered as general advice. Each SBP 29 installation
must be handled separately depending on the hull design and the other electrical and
mechanical systems installed on the vessel.
Reducing flow noise
• The shape of the SBP 29 (or dome around it) must be as streamlined as possible.
• The hull plating in front of the SBP 29 must be as smooth as possible.
Important
Be especially aware of bilge keels and zinc alloy anodes. The keel must be rounded off
without sharp edges. Neither extruding objects nor abrupt transitions must be present.
Reducing machinery noise
• The main engine and relevant auxiliary engines and equipment must be fixed to rigid
foundations to avoid vibrations.
• Any hull structure that may vibrate should be damped or coated to reduce the
vibrations.
The use of shock absorbers or floating rafts may sometimes reduce this noise. The
structure-borne noise may be reduced by isolation, for example by providing vibration
clamping between the SBP 29 and the hull structure.
Reducing propeller noise
• Sufficient clearance between the propellers and the hull, the rudder and the keel must
be provided.
• Place the zinc alloy anodes in places where the water flow is the least disturbed.
• Ensure that the propellers blades are correctly designed and without damages.
• The use of a baffle between the propellers and the SBP 29 may reduce noise
appreciably.
• Static discharges caused by the rotating propeller shaft may be removed by proper
grounding or by mounting a coal brush from the shaft to vessel ground.
Reducing rattle noise
Ensure that no parts near the SBP 29 can rattle as a result of water flow or vibrations.
Reducing interference
Interference from the transmission pulses from other hydroacoustic instruments on
board the vessel is difficult to avoid. The problem may be reduced by choosing the
working frequencies carefully and to some extent by separating the different transducers.
On vessels with a large number of separate hydroacoustic systems installed and in
Summary of Contents for SBP 29
Page 1: ...451253 A November 2019 Kongsberg Maritime AS SBP 29 Sub bottom profiler Installation Manual ...
Page 111: ...451253 A 111 Figure 12 862 216859 Drawing files ...
Page 112: ...112 451253 A Figure 13 307904 SBP 29 Installation Manual ...
Page 113: ...451253 A 113 Figure 14 862 218001 Drawing files ...
Page 114: ...114 451253 A Figure 15 871 219193 SBP 29 Installation Manual ...
Page 115: ...451253 A 115 Figure 16 871 219201 Drawing files ...
Page 116: ...116 451253 A Figure 17 388168 SBP 29 Installation Manual ...
Page 117: ...451253 A 117 Figure 18 871 219187 Drawing files ...
Page 118: ...118 451253 A Figure 19 821 219199 SBP 29 Installation Manual ...
Page 119: ...451253 A 119 Figure 20 388235 Drawing files ...
Page 120: ...120 451253 A Figure 21 871 219198 SBP 29 Installation Manual ...
Page 121: ...451253 A 121 Figure 22 388148 Drawing files ...
Page 122: ...122 451253 A Figure 23 315550 SBP 29 Installation Manual ...
Page 123: ...451253 A 123 Figure 24 430751 Drawing files ...
Page 124: ...124 451253 A Figure 25 871 212984 SBP 29 Installation Manual ...
Page 125: ...451253 A 125 Figure 26 407070 Drawing files ...
Page 126: ...126 451253 A Figure 27 448231_1A SBP 29 Installation Manual ...
Page 127: ...451253 A 127 Figure 28 427512 Drawing files ...
Page 128: ...128 451253 A Figure 29 435680 SBP 29 Installation Manual ...
Page 129: ...451253 A 129 Figure 30 444783 Drawing files ...
Page 151: ......
Page 152: ... 2019 Kongsberg Maritime ...