Figure 11: Jackscrew locations, top view
1.
Lower the baseplate carefully onto the foundation bolts.
The baseplate will rest on top of the foundation on the jackscrews provided on the baseplate.
2.
Adjust the leveling jackscrews, located adjacent to the foundation bolt holes, until the baseplate
rests 25 to 50 mm | 1 to 2 in. above the foundation in order to allow for adequate grouting.
This provides even support for the baseplate after grouting.
3.
Level the baseplate to within 0.167 mm/m | 0.002 in./ft. of the length or width of the baseplate by
adjusting the jackscrews.
•
The maximum total variation from one end or side of the baseplate to the other is 0.38 mm |
0.015 in.
•
Use the equipment mounting surfaces in order to establish the level.
4.
Use a non-bonding (anti-seize) compound such as paste wax to coat the portions of the jackscrews
that will contact the grout.
This facilitates removal of the screws after grouting.
NOTICE:
Do not use oils or liquid wax.
5.
Thread the nuts onto the foundation bolts and hand-tighten.
4.3 Install the pump, driver, and coupling
1.
Mount and fasten the pump on the baseplate. Use applicable bolts.
2.
Mount the driver on the baseplate. Use applicable bolts and hand tighten.
3.
Install the coupling.
See the installation instructions from the coupling manufacturer.
4.3 Install the pump, driver, and coupling
Model 3600 i-FRAME API610 11th Edition / ISO 13709 2nd Edition to current API BB3 Multi-Stage, Axially Split Installa-
tion, Operation, and Maintenance Manual
25