55
Trial run
Performing the trial run
■
Prevent other devices around the product from operating.
Other devices incorporated in the system, such as conveyor lines, could create
dangerous situations, since totes may start to be transferred from upstream when
the trial run is driven.
Check carefully that other conveyors or devices will not operate by trial run.
■
Make sure to check that wiring and controller settings have been carried out
correctly before the trial run.
■
During operation, the transfer speed may not reach the specified value depending on
ambient temperature.
When the start-up inspection has finished, perform the trial run with careful attention
to the following points, and check that operation is correctly performed.
Trial run