If CMAs are not installed, the minimum depth of the cabinet is 1 m (3.28 ft).
For chassis that support only 2.5-inch hard disks, only cabinets with a 1.1 m (3.61 ft) or
greater depth support holding rails and CMAs.
4.4.1 Installing the L-Shaped Guide Rails and Chassis
Scenario
L-shaped guide rails are only for Huawei cabinets.
Procedure
Step 1 Install floating nuts.
1. Determine the position for installing a floating nut according to the
installation plan.
Floating nuts and screws are used together to secure the chassis.
The boundary of two Us is indicated by the smaller spacing between two adjacent
square holes, as shown in
. The boundary between Us is used as a reference
for calculating the device installation space.
Figure 4-4 Spacing of 1U on a mounting bar of a cabinet
2. Put the lower end of a floating nut into the installation hole at the front of
the cabinet.
3. Fasten the upper end of the floating nut to the mounting bar at the front of
the cabinet by using the floating nut hook, as shown in
.
TaiShan X6000 Server
User Guide
4 Installing the X6000
Issue 04 (2020-06-05)
Copyright © Huawei Technologies Co., Ltd.
36