Figure 4-17 Moving the smart cooling product
4. Move the smart cooling product out of the pre-fab.module using a forklift.
Step 14 Install a new smart cooling product.
1. Install the new smart cooling product, and connect structural kits, pipes, and
cables.
2. Perform power-on commissioning for the smart cooling product to verify that
the new smart cooling product is working properly. For details, see documents
delivered with the smart cooling product.
3. Reinstall the removed components.
----End
4.2.2.1 Replacing a T/H Sensor
Prerequisites
●
A T/H sensor needs to be replaced.
●
A spare T/H sensor of the same model is available and functional.
Context
A T/H sensor can be maintained only from the rear door.