3. Using both hands, pull the post-combustion ring
(3, Figure 02) horizontally out of the bottom section.
1a
3
1
Figure 02
4. Lift the dust separator (4, Figure 03) straight upwards,
guide it towards the rear over the retaining bracket
and via the post-combustion ring rail towards the
outside.
4
Figure 03
2.2.1.2 Fitting refractory lining elements
The elements are fitted by following the instructions above
in reverse order. Pay attention to the side nipple on the
post-combustion ring (3, Figure 02). It must always point
towards the left, in the direction of the burner mechanism.
2.2.2 Set-up
Observe the minimum wall clearances (see Chapter 3.4
and 3.5). If required, the boiler door can also be attached
on the left.
7
4 211 326 / 01
InSTALLATIOn