COMMISSIONING AND DECOMMISSIONING
Information for general use
Rev. M / 73023639
82
GasLab Q2
Use angled pincers or pliers to connect the jumper.
A small mirror will also help you to find the connection pins and check that it is
correctly positioned.
You can view the setting by using devices displays and enSuite.
See chapter
7 GasLab Q2 Displays (Operate the Device)
8 Configuration and analysis software enSuite
6.1.4.
Additional conditions for fiscal metering
In the case of fiscal use, the conditions laid down in the relevant approval must be met. This is
ensured by a file in the device that adjusts the settings. For final commissioning, the calibration
switch or security switch (SSW) must be closed. You can attach a seal directly to the SSW (jumper)
to prevent or detect unauthorized access
.
Within the scope of fiscal metering, depending on the regulations of
your country, for the final commissioning the presence of an authorized
person (calibration officer), who carries out officially protected work on
gas-technical plants is required.
For details on the SSW, see Section
Opening and closing the hardware parameter guard
for the approval file see
8.4.10 Fiscal parameters and optional using approval file (Select
The applicable regulations on sealing the device must also be observed during fiscal operation.
Make sure that you comply with these regulations.