43
Chapter 3 Installation
|
Hillstone
Hillstone SG-6000 X-Series Hardware Reference Guide
1.
Make sure the rack is secured to the floor or to the structure of the building. The
area around the installation site has sufficient space for air floor and
maintenance operations.
2.
Use rack-mounting ear to mark the positions of floating nuts on the front rack
posts.
3.
Attach rack-mounting ears to the left and right side panels of the chassis
respectively.
Figure 3-6: Installing Rack-mounting Ears
4.
Load the chassis steadily on the center of the lift platform.
5.
Use the lift to move the chassis to the rack or the cabinet tray, and then move
away the lift.
6.
Install a mounting screw into each of the two aligned holes as shown below. Use
a cross screwdriver to tighten the screws.