Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial COMMISSIONING OPERATION
100
The air conditioning unit works at a current much larger than the rated current (the working current
changes in a large scope in different conditions). The power grid provides unstable voltages and the line
power factor decreases. Therefore, the power capacity should not be less than the maximum power of
the unit.
(4) Check air switches and fuse links for their models and using methods.
1) Commercial air conditioning units must be installed with independent air switches, fuse links, and
similar protectors. Reasonable models and using methods should be selected for air switches and fuse
links.
Remarks:
a. Air switches work for overload and short-circuit protection. Air switches provide a less breaking
current than fuse links and air switches react more slowly than fuse links. The advantage of air switches
is that they can be manually reset after a protection action.
b. Fuse links only work for short-circuit protection. They provide a large breaking current and act
slowly. However, fuses must be replaced after a protection action.
2) Select air switch models according to the power cable diameter and air switch specifications. In
general, the rated current of air switches should be larger than or equal to the load current calculated
based on the line, and less than or equal to the persistent current rating allowed by the conductor.
(5) Check components in the electric box.
In the case of unit power-off, visually check whether any component in the electric box drops during
transportation. Then, check whether any component or cable is loose or drops by hand. For a
large-scale unit, power cable terminals of the patch panel and cable terminals connected with connectors
must be tightened with a sleeve spanner or screwdriver, and tightened once more after two months of
normal operation. Auxiliary contacts of AC connectors cannot be removed because they have been
debugged upon factory departure.
(6) Check the input power.
1) Power consistency check: Measure the power supply to be connected with the air conditioning
unit for its voltage, frequency, three-phase voltage unbalance factor, and frequency offset. Specifications
of the power supply should be consistent with power specifications displayed on the unit nameplate. The
fluctuation range of voltage should be within ±10%.
2) Phase sequence check:
a. After powering on the unit, measure the voltage value between every two of L1, L2, and L3 bits.
In general, the voltage between every two of L1, L2, and L3 bits should approach 208~230 V. If the
measurement result does not match the above-mentioned normal value, check whether the external
power cable is inversely connected.
b. Observe the code displayed on the digital LED of the main board AP7. If the fault code
―U3‖ is
displayed, it indicates that the phase sequence of the external power cable connected with the air
conditioning unit is incorrect. Power off the unit and exchange any two phases among L1, L2, and L3 bits
on one end of the external power cable. Power on the unit and observe the code again. The fault code
Summary of Contents for Ultra Heat GMV-VQ72W/A-F
Page 1: ...Ultra Heat GMV Multi VRF TECHNICAL SERVICE MANUAL R410A Heat Recovery Series ...
Page 30: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial INSTALLATION 26 ...
Page 73: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial INSTALLATION 69 ...
Page 135: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 131 ...
Page 203: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 199 5 4 NCHS4B U ...
Page 205: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 201 5 5 NCHS8B U ...
Page 207: ...Jf00303410 ...