30 Gallon Vibrating Hopper Installation
See F
. 64 for illustration of installed vibrating hopper.
1.
Turn main power switch OFF.
2.
With the steel shaker rod fully assembled and the
3/8 in. OD air line connected to the shaker head, cut
the 3/8 in. OD air line where the 1.3 in. clear vac-
uum transfer hose connects to the steel shaker rod.
3.
Use the splitter fitting (917) to reconnect the 3/8 in.
OD air line that was just cut.
4.
Install the 48 in. section of 3/8 in. OD hose supplied
with the kit into the remaining connection on the
splitter fitting (917).
5.
Connect the other end of the 48 in. section of 3/8 in.
OD air line to elbow fitting (916) on the piloted air
valve.
6.
Connect shop air to elbow fitting (914) on the piloted
air valve. Shop air must be capable of 100 psi
(0.7 MPa, 7 bar).
NOTE:
The piloted air valve must use shop air. Adding a
tee at the system inlet to run the hopper shaker may
impact pump and vacuum transfer performance.
7.
Place steel shaker rod assembly into hopper (901)
with steel rod resting in the hopper groove in the rim
of the hopper.
8.
Place lid (902) on hopper (901).
NOTE:
The hopper shaker will be active while the vac-
uum transfer system is transferring pellets.
NOTE:
The air supplied to the pilot valve from the sys-
tem vacuum must be set to 65% of the shop air supply
supplied to elbow fitting (914) or higher. If the pilot valve
air pressure is lower than this, increase the vacuum
transfer air pressure regulator (E, see F
. 1 on page
11).
F
IG
. 64
To shop air
supply
Splitter fitting
To piloted
air valve
To shaker
head
Piloted air
valve
Hopper
shaker
ti21350a
Summary of Contents for 24T918
Page 16: ...Component Identification 16 333347F ...
Page 103: ...Accessories 333347F 103 ...
Page 129: ...Technical Data 333347F 129 ...