8 OPERATION
This symbol refers to the operations of a Parallel System.
NOTE !
Verify that the input/output connections have been performed by
qualified personnel before connecting mains input voltage and verify that
the equipment is correctly grounded.
Open only the front door, do not remove any panels.
Now you can initiate the start-up procedure of the UPS system.
There is no need for specific knowledge if you follow carefully the step-
by-step instructions given below.
However we recommend that at least the initial procedure should be
performed by an instructed person.
Check after every step for correct reaction of the UPS (LEDs on the panel),
and correct voltage and current measurements, before you proceed to
the next step.
If you encounter any problems during the following procedures, you
should not continue, but contact
GE Global Services
.
Find on the following pages the descriptions of the various procedures of start-up and
shutdown for UPS single and UPS Parallel System
,
divided into the following principal
chapters.
8.1
PROCEDURES FOR SINGLE
SitePro
8.2 PROCEDURES
FOR
SitePro
PARALLEL SYSTEM