03/07/03
14-1
Section 14
FINISH START-UP
1.
Be sure customer has current backup copies of the release and applications disks stored in a
safe place. As an ASR, you may wish to make copies for yourself.
2.
Answer questions and/or demonstrate the optional commands or devices such as: user and
cron commands, disable and enable commands, the diagnostic commands, the system
override switches, and modem polling procedure (including modem phone number, baud
rate, and password).
3.
Explain the proper use of the site manager's key; especially that it should
never
be left in the
ON
position. For an Islander, the site manager's key is located in the head of the unit.
4.
Close and secure all doors for the pump control unit(s) and island card reader(s) and
Islander.
5.
Lock out the test cards/keys.
6.
Generate a printout showing a few transactions with quantity, pump fuel assignments,
limitation codes, authorization codes, and pulse rates. Use the commands
P DA
,
P TR
,
P
PU
,
P A
,
P LI
,
P DI
,
P PR
,
P PRO
. Also generate a printout showing any configuration
changes that were made. Include these printouts with the Start-up form.
✍
11. CUSTOMER KNOWLEDGE
Briefly describe the customer's understanding of the CFN Series System. Write in the amount of
time spent on training and who was trained.
Check to see that the test cards are locked out (Step 5) and indicate the name of the person with
whom the test cards were left.
Indicate whether backups of the system and any configuration changes were made.
Fill in any remarks you may have regarding the start-up or the system. Use additional sheets if
necessary and staple to form. Be sure to include any configuration changes that you may have
done at start-up.
12. ATTACH PRINTOUTS
Generate printouts using the commands noted (Step 6) and attach to the Start-Up Form.
13. PARTS USED
Any defective parts resulting from a start-up should be returned with a completed GASBOY
Warranty Service Report (WSR). Follow directions on the form.
14. SITE LAYOUT
Sketch a layout of the site. Be sure to include the location of the system, hose outlets, data
terminals, external modems, circuit breakers and distances between units.
Check off the appropriate box for
Start-up Complete
,
Start-Up Incomplete
, and fill in the
number for
Number of Start-Up Attempts
.
Summary of Contents for CFN Series
Page 1: ...CFN SERIES SITE CONTROLLER II ISLANDER II START UP MANUAL C01665 GASBOY INTERNATIONAL LLC ...
Page 2: ......
Page 8: ...CFN Series System Contents 4 03 07 03 ...
Page 24: ...CFN Series System 2 12 03 07 03 ...
Page 25: ...Site Information 03 07 03 2 13 ...
Page 26: ...CFN Series System 2 14 03 07 03 ...
Page 38: ...CFN Series System 4 6 03 07 03 ...
Page 56: ......
Page 58: ......
Page 72: ......
Page 82: ...CFN Series System 9 10 03 07 03 ...
Page 104: ...CFN Series System 12 12 03 07 03 ...
Page 108: ...CFN Series System 13 4 03 07 03 ...