Page 9
INSTALLATION - 2
Models 40J - 60J
The main gas valve is fitted with a bypass system (internal or external depending on the model)
the bypass allows pilot pressure to be maintained whilst the flame is verified.
2.10.1
GAS VALVE WITH PILOT GAS LINE
An individual wiring diagram for the boiler is located on the inside cover of the control box.
When referring to the electrical specification of the boiler, the reference number located on the
rear inside wall of the control box and the wiring diagram number should be quoted.
The audible alarms provided are mounted on the side of the control panel, if not audible they
should be repositioned where they can be heard by a person competent to take the appropriate
action should the alarm be activated.
Unless otherwise specified, the alarms supplied will be mains voltage models. Unless otherwise
specified all models are supplied with burner motors and feedwater pump motors arranged for
operation on a three phase supply.
The power ratings and requirements are given in
Appendix A - TI-117-J Series Dimensions &
Specification.
2.11
ELECTRICAL REQUIREMENTS
2.12
STEAM PRESSURE GAUGE
The steam pressure gauge assembly should be assembled in accordance with
Figure. 8
using a
suitable sealant on all joints.
The gauge should be facing front towards the electrical control box and/or the operator of the
boiler.
Screw the assembly into the top of the boiler and connect the copper tube from the pressure
controller located on the side of the control box to the nipple provided on the assembly.
Test Point
Steam Pressure Gauge
Steam Cock
Syphon
Plugged
Figure. 8 - Steam Pressure Gauge
Summary of Contents for J Series
Page 2: ...JGASUK IOMM 2015 2 Fulton Ltd Page II ...
Page 54: ...JGASUK IOMM 2015 2 Fulton Ltd Page 48 APPENDIX A ...
Page 58: ...JGASUK IOMM 2015 2 Fulton Ltd Page 52 APPENDIX A ...
Page 60: ...JGASUK IOMM 2015 2 Fulton Ltd Page 54 ...
Page 62: ...JGASUK IOMM 2015 2 Fulton Ltd Page 56 ...