24
Connecting the Fronius IG Plus to the Public
Grid (AC)
AC-side Termi-
nals
One-phase inverter
Three-phase inverter
Two-phase inverter
Legend:
L1 Phase conductor
L2 Phase conductor
L3 Phase conductor
PE PE conductor
N Neutral conductor
(a) Terminal for grounding rod
(b) Terminal for possible grounding
of the solar module frame
(c) ‘US Sense’ terminal (for USA)
max. cable cross section 25 mm²
Important
The resistance in the leads to the AC side connection terminals
must be as low as possible for optimal functioning of mains network moni-
toring.
Monitoring the
Mains Net-
work
For large photovoltaic systems, several Fronius IG Plus units can be
connected in parallel.
To ensure symmetrical feeding, connect the inverters uniformly to all 3
phases.
Installations
with Several
Inverters
(a)(b)
(c)
(a)(b)
(c)
(a)(b)
(c)
NOTE
Make sure that the network neutral conductor is grounded.
Summary of Contents for Fronius IG Plus 100
Page 2: ......
Page 4: ...ud_fr_st_et_01382 012008...
Page 14: ...6...
Page 15: ...7 General Information...
Page 16: ...8...
Page 20: ...12...
Page 21: ...13 Installation and Startup...
Page 22: ...14...
Page 71: ...63 Closing Fronius IG Plus Closing Froni us IG Plus 1 1 4 2 7 3 5 6...
Page 77: ...69 Operation...
Page 78: ...70...
Page 118: ...110...
Page 119: ...111 Troubleshooting and Maintenance...
Page 120: ...112...
Page 141: ...133 Appendix...
Page 142: ...134...
Page 152: ...144...
Page 155: ......