INTERNAL DOOR & WINDOW FRAMING
Apply the internal sides on either side of the door.
Trim to fit if necessary. Use 5 x 60mm nails for each
board to secure.
231
231
Apply the 45mm boards on top of beaded panel.
Ensure this is flush to the inner framing. Use 5 x
30mm nails to secure. Repeat this process on the
opposite side.
232
232
Apply the side framing, using 5 x 30mm nails per
board.
236
236
238
238
Repeat the same process for the window framing.
Use 4 x 30mm nails to secure.
235
235
The top frame will sit on top of the side boards.
Ensure both ends are flush to the side framing
edge. Trim if necessary.
233
233
Fix into place using 6 x 30mm nails.
234
234
Apply the overlapping framing. Ensure flush
around all edges and trim if necessary.
237
237
Use 5 x 30mm nails per side 45mm board. Finish
with the top board using 4 x 30mm nails to secure.
36