Components for removing valve locations
When valve locations are removed, the tie rods must
be adapted accordingly.
You will require:
Components
Typ
Basis tie rod
(graduation: 2, 4, 6 to 22)
CPA..-ZA-2
.
.
CPA..-ZA-22
If necessary, short tie rod screw (for valve termi-
nals with an even number of valve locations)
CPA..-ZA-SK
Long tie rod screw (for valve terminals with an
odd number of valve locations)
CPA..-ZA-SL
The table below shows the tie rod components which
you will require to adapt the length of the tie rod.
Number*
)
Starting basis: valve terminals
with an even number of valve
locations
Starting basis: valve terminals
with an odd number of valve
locations
- 1
2 basis tie rods and
2 long tie rod screws
2 short tie rod screws
- 2
2 basis tie rods
2 basis tie rods
- 3
2 basis tie rods and
2 long tie rod screws
2 basis tie rods and
2 short tie rod screws
> - 3
2 basis tie rods or.
2 long tie rod screws
2 basis tie rods or
2 short tie rod screws
*
)
number of valve locations to be removed
5. Maintenance and conversion
5-26
CPA... 9808A
Summary of Contents for CPA VI Series
Page 2: ......
Page 4: ...Order no 173 515 Title MANUAL Designation P BE CPA GB II CPA 9808A...
Page 15: ...Chapter 1 System summary 1 System summary CPA 9808A 1 1...
Page 29: ...Chapter 2 Fitting 2 Fitting CPA 9808A 2 1...
Page 35: ...Kapitel 3 Installation 3 Installation CPA 9808A 3 1...
Page 54: ...3 Installation 3 20 CPA 9808A...
Page 55: ...Chapter 4 Commissioning 4 Commissioning CPA 9808A 4 1...
Page 69: ...Chapter 5 Maintenance and conversion 5 Maintenance and conversion CPA 9808A 5 1...
Page 97: ...Technical appendix A Technical appendix CPA 9805NH A 1...