5. Commissioning and configuration
5.1. Switching on
a) For the first switch-on only, first set all MCBs and RCDs (if fitted) to the off
(down) position.
b) Switch on power to the rack, and check that the three yellow power supply
LEDs L1, L2 and L3 are on, indicating that power from all three phases is
reaching the power supply section. If not, switch off, check wiring and
repeat.
c) If RCDs are fitted, switch them on. If any RCDs trip at this stage, there is an
earth wiring fault in the dimmer rack.
d) Switch on MCBs, one by one. If any RCDs trip at this stage, there is a power-
fault in the power assembly.
5.2. Power and signal indicators
The following status indicators are provided on the control panel. Check that
their status is correct before continuing:
page 31
Smartrack User Manual
Version 1.2
L1
DMX
✔
L2
DMX
✘
temp
L3
level
dimmer profile
speed
enter
0 0 1
Smartrack Control Panel,
showing default start
address (001)
0 0 1