2.
Use a forklift or pallet jack to move the packaged cabinets to the installation site, or as close as possible,
before unpacking. If possible, move the cabinets using the pallet. Insert the forklift or pallet jack forks from
the right side of the pallet (facing the cabinet), between the supports on the bottom of the pallet. If the
cabinets must be moved using the cabinet front or rear fork lift slots, see the caution statement at the
beginning of this procedure.
Do not tilt the UPS cabinet more than 10º from vertical or the cabinet may tip over.
ATTENTION!
Ne pas incliner les armoires d’onduleur à plus de 10 degrés de la verticale puisqu’elles pourraient se renverser.
3.
Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft) on each side for
removing the cabinet from the pallet.
NOTE
The ISBM and UPM sections are shipped with debris shields covering the ventilation
grills on top of the sections (see
). Do not remove the debris shields until
installation is complete.
4.
Remove the protective covering from the cabinet.
5.
Remove the packing material, and discard or recycle in a responsible manner.
6.
Inspect the contents for any evidence of physical damage, and compare each item with the Bill of Lading.
If damage has occurred or shortages are evident, contact an Eaton service representative immediately to
determine the extent of the damage and its impact on further installation.
NOTE
While waiting for installation, protect the unpacked cabinet from moisture, dust, and
other harmful contaminants. Failure to store and protect the UPS properly may void your
warranty.
Summary of Contents for Power Xpert 9395P-600/600
Page 8: ......
Page 226: ...16400071007 164000710 07...