Access Power Solutions Installation Guide (APS6-400 Series)
14
Copyright © 2009-2010 Eaton Corporation. All Rights Reserved.
IPN 997-00012-53B December 2010
Installation Tasks
Before starting the installation, review the following information:
Required Equipment and Tools on page
Warnings and Cautions on page
Inspecting the Equipment and Reporting Damage on page
Complete the Installation tasks in the following order:
Task Description
Reference
1
Check the AC Supply and Grounding
See details on page
2
Customize the APS
See details on page
3
Mount the APS in the Rack
See details on page
4
Connect External Input/Output Cabling (if required)
See details on page
5
Connect the DC Load and Battery Cables
See details on page
6
Install the Batteries
See details on page
7
Mount the Battery Temperature Sensor
See details on page
8
Connect the AC Supply Cable
See details on page
Task 1 - Check the AC Supply and Grounding
It is important that the ac supply for the Access Power Solutions dc power system includes the
correct levels of protection.
Step 1 - High ac voltage protection at the site
1
Check if the ac voltage is expected to exceed 275V (L-N or L1-L2).
2
If so, then it is strongly recommended that an external high voltage protection
unit (HVPU) be installed. This will automatically disconnect the ac at high
voltage and reconnect it at normal voltage.
3
Install the HVPU as in the following diagram.
4
Connect the High VAC alarm output to one of the Digital Inputs on the I/O
Interface Board (see the diagram on page
The High VAC alarm signal lines must be isolated from the ac supply by a voltage-
free relay contact.