ESIE05-04
Disassembly and Maintenance
Part 5 – Disassembly and Maintenance
5–125
3
5
1
5
1.16.3 Removal of Electrical Parts Box
Warning
Be sure to wait 10 minutes or more after turning off all power supplies before disassembling work.
Procedure:
Step
Procedure
Points
Q
Remove the left and right side
panels, operation display
cover and front grille
according to the procedures
for their removal.
The left and right side panels
have to be taken off in order to
remove the front grille.
1
Remove the
(1) thermistor,
(2) heater connector
and
(3) rubber clip
connected to the PC
board.
2
Remove the 2 screws
fastening the electrical
parts box to the units.
3
Lift the electrical parts
box and remove by
moving toward the right.
Summary of Contents for FHQ100BUV3B
Page 1: ...Service Manual ESIE05 04 R 410A Sky Air Indoor...
Page 2: ......
Page 20: ...ESIE05 04 1 2 Part 1 System Outline 3 1 1 5...
Page 62: ...General Outline ESIE05 04 1 44 Part 1 System Outline 3 1 1 4 5...
Page 78: ...ESIE05 04 1 60 Part 1 System Outline...
Page 112: ...Wiring Diagrams ESIE05 04 1 94 Part 1 System Outline 3 1 1 4 5...
Page 140: ...ESIE05 04 2 2 Part 2 Functional Description 3 1 2 5...
Page 164: ...ESIE05 04 3 2 Part 3 Troubleshooting 3 1 3 5...
Page 206: ...Error Codes ESIE05 04 3 44 Part 3 Troubleshooting 3 1 3 4 5...
Page 224: ...Additional Checks for Troubleshooting ESIE05 04 3 62 Part 3 Troubleshooting 3 1 3 4 5...
Page 226: ...ESIE05 04 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Page 252: ...ESIE05 04 5 2 Part 5 Disassembly and Maintenance 3 1 5...
Page 384: ...Disassembly and Maintenance ESIE05 04 5 134 Part 5 Disassembly and Maintenance 3 1 5 5...
Page 390: ...ESIE05 04 vi Index 3 1 4 5 W Wiring diagrams Indoor units k 1 61...