2 PILLAR INSTALLATION
Fig. 13
- Insert pillars (
A
) into feet (
B
).
Note: The pillars feature reinforcements on the upper side.
Note:
The recesses
(C)
on the top edge of the pillar (that will act as drain holes for the gutters) must
be positioned inside the structure (det. X).
Apply a bead of silicone in the pillar/foot areas as shown in
(det. Y)
.
Fig. 14
Fix the pillars to the feet using M8x16 BUTTON screws (
A
) (q.ty 4 each).
Note: Should it not be possible to reach the screws because the pillar is against a wall, after the
structure installation it is COMPULSORY to use the wall-mounting system on the upper beam.
A
B
A
B
A
B
A
A
Det. X
C
Det. Y
IMPORTANT: the 4 pillars must be positioned so as to obtain a “PERFECTLY” flat structure; this is fundamental to ensure that rainwater correctly flows inside the pillars and does not spill over the