7.5 Checking and replacing internal modules
Before a control or exchange of internal modules the system must be released by activating the corresponding
D02 fused circuit-breaker.
For mounting or dismounting of modules please see chapter 6.5 „Connection and installation of internal modules“
and all warning notices!
NOTE!
On the SU S
+
modules you will find a Service push button that can be used for initial commissioning and for testing
purposes. When it is pressed, the controller software displays addresses and characteristics of the selected module
directly on the graphic display of the controller.
7.6 Checking and replacing external modules
For mounting and dismounting of a module please see chapter 6.8 „Connection and installation of external mo-
dules“. Please observce the following:
Set the address for the DLS bsu module. Avoid assigning the same address more than once as this causes
stoppages.
To ensure that replaced external modules function correctly under the controller they must first be identified,
activated and their parameters set up with the controller software.
On the SU S
+
modules you will find a Service push button that can be used for initial commissioning and for testing
purposes. When it is pressed, the controller software displays addresses and characteristics of the selected module
directly on the graphic display of the controller.
7.7 Powering up the system
Switch on the mains supply at the load disconnector.
Switch on the controllers with <<Release device>> menu option.