7
Commissioning
7.1
Safety
Personnel:
The conductor rail system must only be commissioned and operated for the first time after a repair by qualified electricians!
These qualified electricians have to meet the requirements described in section 2.2.1.
Required protective equipment:
Requirement:
WARNING!
Risk of injury due to improper commissioning!
Improperly performed commissioning can lead to dangerous situations for personnel.
→
Before commissioning, carry out the inspections on the inspection list of the manufacturer.
→
Always measure the insulation resistance before commissioning the system. This must be done in
compliance with the local technical standards, guidelines and legislation
→
Always make sure that all of the assembly and installation work has been fully completed before
commissioning the system
→
Always make sure that all of the components have been properly installed before commissioning
the system
CAUTION!
Before working on these components!
→
Disconnect the conductor rail system
from the power supply according to the 5 safety rules
and
secure it against being switched back on.
For the 5 safety rules, see section 2.6
CAUTION!
Before switching the system on!
→
Every time before the device or system is started, measure the insulation resistance according to
locally applicable technical standards, directives and legal regulations.
→
Perform the required country-specific electrical tests