HOOK INSPECTION 

Hooks damaged from chemicals, deformations or cracks or that 

have more than a 10° twist from the plane of the unbent hook or 

excessive opening or seat wear must be replaced. 

Also, hooks that are opened and those that allow the latch to 

disengage the tip, must be replaced. 

Any hook that is twisted or has excessive throat opening indicates 

abuse or overloading of the unit. Other load-sustaining components 

of the hoist should be inspected for damage. 

The chart below should be used to determine when the hook must 

be replaced. To measure throat opening, depress the latch against 

the hook body as shown below.

MEASURE 

OPENING

Hoist Rated Load Tons (kg)

Replace Hook When Opening is 

Greater Than:

inches

mm

1/2 (500)

1.19

30.2

1 (1000)

1.34

34

2 (2000)

1.71

43.5

3 (3000)

2

50.9

5 (5000)

2.52

64

Also, check to make sure that the latch is not damaged or bent and 

that it operates properly with sufficient spring pressure to keep the 

latch tightly against the tip of the hook and allow the latch to spring 

back to the tip when released. If the latch does not operate properly, 

it should be replaced.

LOAD CHAIN

CLEANING AND INSPECTION

First clean the load chain with a non-acid or non-caustic type solvent 

then slack the chain and make a link-by-link inspection for nicks, 

gouges, twisted links and excessive wear or stretching. Worn chain 

should be gaged throughout its entire length and replaced if beyond 

serviceable limits. 

To determine if load chain should be continued in service, check 

gage lengths as indicated in figure below. Chain worn beyond length 

indicated, nicked, gouged or twisted should be replaced before 

returning hoist to service. Chain should be clean, free of twists and 

pulled taut before measuring. In cases where the wear is localized 

and not beyond serviceable limits, it is sometimes possible to 

reverse the load chain, end for end, and allow a new section to take 

the wear. Proper installation of the load chain is covered in section 

on Reeving Load Chain (page 7).

Hoist Rated Load 

Tons (kg)

Chain Stock 

Diameter - in. (mm)

No. of Links to 

gage

Max. Length 

Allowable for 

used Chain - in. 

(mm)

1/2 (500)

0.236 (6)

11

8.50 (215.9)

1 (1000)

0.236 (6)

11

8.50 (215.9)

2 (2000)

0.315 (8)

11

11.33 (287.9)

3 (3000)

0.315 (8)

11

11.33 (287.9)

5 (5000)

0.394 (10)

11

14.17 (359.9)

Hand Chain

0.198 (5)

11

11.55 (293.3)

Note that worn chain can be an indication of worn hoist 

components. For this reason, the hoist’s chain guide roller and 

liftwheel should be examined for wear and replaced as necessary 

when replacing worn chain.

Also, load chains are specially heat treated and hardened and should 

never be repaired.

Using other than CM-supplied load chain may cause the chain to 

jam in the hoist and/or allow the chain to break and the load to drop.

TO AVOID INJURY:

Due to the size requirements and physical properties, use only 

CM Hoistaloy

®

 load chain in the Series 622A Hand Hoist.

IMPORTANT: Do not use replaced chain for other purposes such 

as lifting or pulling. Load chain may break suddenly without 

visual deformation. For this reason, cut replaced chain into short 

lengths to prevent use after disposal.

Before returning chain to service or after replacing a load chain, 

lubricate liberally with Lubriplate Bar and Chain Oil 10-R (Fiske Bros. 

Refining Co.) or equal lubricant. Remove excess lubricant from the 

chain by wiping with a cloth.

HAND CHAIN

Hand chain should be cleaned, inspected and gaged in the same 

manner as load chain. 

As received from the factory, the hand chain contains an unwelded 

link. This link can be placed in a vise and twisted open to facilitate 

changing chain length. Please note that opening and closing of 

the connecting link more than twice is not recommended. Also, 

connecting links must not be made by cutting the weld side of a 

standard hand chain link.

Hand chain should be assembled to handwheel free from twists with 

weld on vertical link facing inwards towards handwheel and weld on 

horizontal link facing towards the handwheel side plate.

Care must be taken to assure that there is no twist in the  

hand chain loop.

LUBRICATION

The Lubricants used in and recommended for the Series 622A Hand 

Hoist may contain hazardous materials that mandate specified 

handling and diposal procedures.

AVOID CONTACT AND CONTAMINATION:

Handle and dispose of lubricants only as directed in applicable 

material safety data sheets and in accordance with applicable 

local, state and federal regulations.

Lubricate load chain with a light coat of Lubriplate Bar and Chain 

Oil 10-R (Fiske Bros. Refining Co.) or equal lubricant. Be sure the 

lubricant reaches the bearing surfaces between the links. Remove 

excess oil from the chain.

Summary of Contents for 2208A

Page 1: ...1 2 3 Y 5 TONNE 500 1000 2000 3000 Y 5000 KG Siga todas las instrucciones y advertencias para inspeccionar mantener y operar ste polipasto El uso de cualquier polipasto presenta algunos riesgos de da...

Page 2: ...to y centros de servicio situados estrat gicamente en Estados Unidos y Canad Estas instalaciones se han seleccionado en base a su capacidad demostrada en la reparaci n de equipos y suminstro de piezas...

Page 3: ...ted load 27 Report malfunctions or unusual performances of a hoist after it has been shut down until repaired 28 NOT operate a hoist on which the safety placards or decals are missing or illegible 29...

Page 4: ...Columbus McKinnon Corporation cannot be responsible for applications other than those for which CM equipment is recommended 1 chain fall SPECIFICATIONS Product Code Rated Capacity tons Standard Lift f...

Page 5: ...hoist frame for dents or cracks and inspect the load chain for nicks and gouges If shipping damage has occurred refer to the packing list envelope on the carton for claim procedure Operating a unit wi...

Page 6: ...of inspection must be determined by the individual application and are based upon the type of service to which the hoist will be subjected The inspection of hoists is divided into two general classif...

Page 7: ...11 11 33 287 9 3 3000 0 315 8 11 11 33 287 9 5 5000 0 394 10 11 14 17 359 9 Hand Chain 0 198 5 11 11 55 293 3 Note that worn chain can be an indication of worn hoist components For this reason the hoi...

Page 8: ...can 28619 1 gal 3 8L can DISASSEMBLY Two points of caution to be observed in disassembly are 1 Loose rollers and bearing balls are used in various locations in the units Care must be taken so as to n...

Page 9: ...feet 1 5M long Run chain thru the hook block first link around the sheave must stand on edge and up to the dead end block Secure chain to dead end block using the stud nut and cotter pin Refer to ill...

Page 10: ...When ordering replacement parts it is recommended that consideration be given to the need for also ordering such items as gaskets fasteners insulators etc These items may be damaged or lost during di...

Page 11: ...15 1 Loose End Pin includes 2 Cotter Pins 22921A 22805A 22927A 22523A 622A 16 1 Chain Guide Roller 22922A 22806A 22827A 22524A 622A 17 1 Upper Hook Assembly includes Hook with Latch Hook Block Bearing...

Page 12: ...10 Manual P N 192052171 Rev AA May 2018 ENGLISH ENGLISH SERIES 622A HAND HOIST EXPLODED VIEW NOTE Metric Tools Required for Fasteners...

Page 13: ......

Page 14: ...uya acci n de sujeci n NO sea segura se debe eliminar la holgura cuidadosamente 26 NO se debe utilizar el polipasto hasta que todas las personas est n alejadas de la carga 27 Si el polipasto presenta...

Page 15: ...e equipos que cumplan con los c digos de seguridad estatales y nacionales Columbus McKinnon Corporation no puede hacerse responsable de los usos distintos a aquellos para los que se recomienda el equi...

Page 16: ...embalaje que se encuentra en la caja para obtener informaci n acerca del procedimiento de reclamos ADVERTENCIA Si se pone en funcionamiento una unidad con da os externos evidentes la carga podr a cae...

Page 17: ...ue est haciendo y utilice el sentido com n No utilice el polipasto si est cansado distra do o bajo la influencia de drogas alcohol o medicamentos que reduzcan el control MANTENIMIENTO INSPECCI N Para...

Page 18: ...ena y realice una inspecci n eslab n por eslab n para verificar que no presenten cortes perforaciones torsi n desgaste o tensi n excesivos Se debe calibrar la cadena en toda su extensi n y se debe ree...

Page 19: ...Corning Corp o una equivalente las roscas de la manivela los engranajes los rodillos de la rueda de elevaci n los rodillos del rodamiento del engranaje los mu ones de la gu a de la cadena y el pasado...

Page 20: ...elevaci n hasta que aproximadamente 2 pies 0 6 mm de cadena hayan pasado por la rueda de elevaci n En este momento se debe retirar el alambre de la cadena Retire el pasador de chaveta del pasador de...

Page 21: ...el C digo B30 16 Polipastos elevados de la Sociedad Americana de Ingenieros Mec nicos American Society of Mechanical Engineers ASME que se puede obtener de ASME Order Department 22 Law Drive Box 2300...

Page 22: ...1 Pasador de extremo suelto incluye 2 pasadores de chaveta 22921A 22805A 22927A 22523A 622A 16 1 Rodillo de gu a de la cadena 22922A 22806A 22827A 22524A 622A 17 1 Conjunto del gancho superior incluye...

Page 23: ...polipasto y el kit del extremo muerto no hay piezas individuales disponibles para reparaciones Conjunto del bloque del gancho inferior A excepci n del pestillo del gancho no hay piezas individuales di...

Page 24: ...PAS Signaler les dysfonctionnements ou les performances nhabituelles d un palan apr s qu il a t arr t jusqu ce qu il soit r par MISE EN GARDE Un mauvais fonctionnement d un palan peut cr er une situat...

Page 25: ...on La Soci t ne peut tre tenue responsable des applications autres que celles pour lesquelles l quipement de CM est recommand 1 chain fall 1 chute de cha ne SP CIFICATIONS Code produit Capacit nominal...

Page 26: ...sont survenus lors de l exp dition se r f rer l enveloppe de la liste de colisage sur la bo te pour la proc dure de r clamation ATTENTION L utilisation d une unit pr sentant des dommages externes vide...

Page 27: ...PECTION Pour maintenir un fonctionnement continu et satisfaisant une proc dure d inspection r guli re doit tre initi e afin que les pi ces us es ou endommag es puissent tre remplac es avant qu elles n...

Page 28: ...e bout bout et permettre une nouvelle section de prendre l usure L installation correcte de la cha ne de levage est d crite dans la section sur la cha ne de levage de la charge page 28 NOMBRE DE LIENS...

Page 29: ...nes des tourillons collier 3 et 5 tonnes goujon mort 3 et 5 tonnes REMARQUE Pour assurer une dur e de vie extra longue et des performances optimales veillez lubrifier les diff rentes parties du palan...

Page 30: ...la cha ne en vous assurant qu il n y a pas de torsion jusqu la goupille d extr mit libre et glisser la goupille dans le dernier maillon de la cha ne Faites glisser la goupille d extr mit libre dans l...

Page 31: ...crochet sup rieur et inf rieur MAINTENANCE PR VENTIVE En plus de la proc dure d inspection p riodique un programme de maintenance pr ventive devrait tre mis en place pour prolonger la dur e de vie du...

Page 32: ...A 22522A 622A 15 1 Goupille d extr mit libre comprend 2 goupilles fendues 22921A 22805A 22927A 22523A 622A 16 1 Rouleau de guide de cha ne 22922A 22806A 22827A 22524A 622A 17 1 Ensemble de crochet sup...

Page 33: ...du kit de verrouillage du kit de suspension du palan et du kit Dead End les pi ces individuelles ne sont pas disponibles pour les r parations Assemblage du crochet inf rieur sauf pour le crochet loqu...

Page 34: ...TY SET FORTH ABOVE SELLER MAKES NO OTHER WARRANTIES WITH RESPECT TO THE GOODS WHETHER EXPRESSED OR IMPLIED INCLUDING ANY WARRANTIES OF MERCHANTABILITY FITNESS FOR A PARTICULAR PURPOSE QUALITY AND OR T...

Reviews: