BAG SEAL CUFF (OPTIONAL)
The bag seal cuff is a feature that prevents dust from coming out of the bulk bag during the
filling process.
A. Bag Cuff Inflate Switch
The operator presses the blue PB to inflate and bag seal cuff. Check the pressure on the
regulator, to make sure the pressure is between 3-5 PSI to start. Adjust as need to make a
good seal inside the bulk bag sleeve. Once the pressure is determined set the regulator by
locking the regulator. Installing the BB neck on to the filler head is a manual operation and
will need to be performed at the beginning of each fill cycle.
B. Regulator and Gauge:
The regulator, gauge and quick dump exhaust valve are mounted directly to the bulk bag
filler head. The pressure adjustment was factory set to 3-5 PSI, however, this will need to
be fine adjusted in the field using the customer's bulk bag.
Summary of Contents for 520
Page 1: ...1 CBE 520 BULK BAGGER Safety Installation Operation Maintenance ...
Page 10: ...10 CHAPTER 1 General Information ...
Page 14: ...14 CHAPTER 2 INSTALLATION GUIDE ...
Page 18: ...18 CHAPTER 3 LOAD CELL WIRING ...
Page 22: ...22 Figure 3 500 Series Bottom View ...
Page 23: ...23 CHAPTER 4 COMPONENT DESCRIPTION ...
Page 26: ...26 CBE DENSIFYING DECK ...
Page 27: ...27 CHAPTER 5 OPERATIONAL SEQUENCE ...
Page 33: ...33 CHAPTER 6 Conveyors Setup ...
Page 38: ...38 CHAPTER 7 PLC and Timers and Adjustments ...
Page 43: ...43 CHAPTER 8 WEIGH CONTROLLER And ADJUSTMENTS ...
Page 45: ...45 ...
Page 48: ...48 See attached Documentation For the Controller specifically Used on your machine ...
Page 49: ...49 Chapter 9 MAINTENANCE ...
Page 51: ...51 CHAPTER 10 TROUBLESHOOTING ...
Page 55: ...55 ...
Page 57: ...57 CHAPTER 12 PLC and TIMER ADJUSTMENTS ...
Page 61: ...61 DRAWINGS AND SCHEMATICS See attached Schematics And Drawings specific for your machine ...