RECEIPT AND INSPECTION
After uncrating the bulk bagger, a check should be made to see that all items ordered have been received
and that all equipment is in good condition.
Any damage incurred in shipment should be reported immediately to the delivering carrier and a claim for
the damage should be filed. Also notify Choice Bagging Equipment, Ltd. so that replacement or repair
may be initiated.
If severe damage has occurred, verify the damage with written reports AND
pictures to Choice Bagging Equipment and call the trucking company or transportation provide.
1. Determine location of all switches.
2. Be sure all guards are in place and observe all warning signs.
3. Check and maintain all oil levels with proper specific oil( if equipped).
4. Be sure all electrical equipment is free of any accumulation of water before installing.
CAUTION AND WARNINGS
1. Observe extreme caution when switches are turned on. Operation may start automatically
after a time delay.
2.
DO NOT
open junction boxes or control panels unless you are a qualified technician. Be
sure
POWER IS OFF
. Except when electricians are performing maintenance, electrical
enclosures and junction boxes should
REMAIN SECURELY CLOSED
.
3.
STOP
machine and disconnect power supply before servicing or repairing. Maintenance
and adjustments must be performed with all electrical power supplies disconnected unless
otherwise specified in this manual.
4.
READ COMPLETELY
any information associated with this bulk bagger. There is an
additional manual included for the GSE controller.
5.
DO NOT
attempt to defeat any safety switches. Serious injury could result. (If applicable)
6. While machine control power is ON, do not activate limit switches manually. Serious injury
and/or machine damage could result. Disable machine before attempting any maintenance
or manual testing of components. (if applicable)
7. If additional wire runs are added to any junction box or control panel, wiring practice should
be such as to maintain prevailing electrical hazard classification.
8. High-pressure air systems are dangerous.
DO NOT
service or trouble-shoot systems with
air supply on. Be sure to bleed off any trapped air before working on components since it is
possible to have high pressures trapped in airlines and cylinders, etc.
Summary of Contents for 520
Page 1: ...1 CBE 520 BULK BAGGER Safety Installation Operation Maintenance ...
Page 10: ...10 CHAPTER 1 General Information ...
Page 14: ...14 CHAPTER 2 INSTALLATION GUIDE ...
Page 18: ...18 CHAPTER 3 LOAD CELL WIRING ...
Page 22: ...22 Figure 3 500 Series Bottom View ...
Page 23: ...23 CHAPTER 4 COMPONENT DESCRIPTION ...
Page 26: ...26 CBE DENSIFYING DECK ...
Page 27: ...27 CHAPTER 5 OPERATIONAL SEQUENCE ...
Page 33: ...33 CHAPTER 6 Conveyors Setup ...
Page 38: ...38 CHAPTER 7 PLC and Timers and Adjustments ...
Page 43: ...43 CHAPTER 8 WEIGH CONTROLLER And ADJUSTMENTS ...
Page 45: ...45 ...
Page 48: ...48 See attached Documentation For the Controller specifically Used on your machine ...
Page 49: ...49 Chapter 9 MAINTENANCE ...
Page 51: ...51 CHAPTER 10 TROUBLESHOOTING ...
Page 55: ...55 ...
Page 57: ...57 CHAPTER 12 PLC and TIMER ADJUSTMENTS ...
Page 61: ...61 DRAWINGS AND SCHEMATICS See attached Schematics And Drawings specific for your machine ...