5 | Installation
Büchi Labortechnik AG
24/102
Operation Manual Pure Chromatography Instruments
5
Installation
5.1
Before installation
NOTICE
Instrument damage due to switching it on too early.
Switching on the instrument too early after transportation can cause damage.
u
Climatize the instrument after transportation.
5.2
Installation site
The installation site must meet the following requirements:
Firm, level surface.
Take into account the maximum product dimensions and weight. See Chapter 3.5
"Technical data", page 18
Clearance on each side of the instrument must be at least 200 mm.
Do not expose the instrument to any external thermal loads, such as direct solar
radiation.
Do not expose the instrument to increased electromagnetic emissions.
Electromagnetic fields in the frequency range between 200 to 300 MHz can cause
the instrument to operate incorrectly.
Make sure that the installation site meets the requirements of the safety data
sheets for all solvents and samples used.
NOTE
Make sure that the power supply can be disconnected at any time in an emergency.
5.3
Securing against earthquakes
The instrument has an earthquake fixing point to protect the device against falling.
1
Fig. 7: Securing against earthquakes
1
Fixing point
u
Tie the lashing mount to a fixed point using strong cord or a wire.
All manuals and user guides at all-guides.com