4 .4 Filling and draining the installation
-
Check the attachment of the pipes, that the connectors
are tight and that the hydraulic module is stable.
-
Check the direction of circulation of the water and that
all of the valves are open.
-
Fill the installation.
-
Deactivate the non-return valves.
-
Position the directional valve in intermediate position.
-
When filling, do not operate the circulation pump, open
all of the drains of the installation and the drains of the
hydraulic module (
P
and
A
) to evacuate the air in the
pipes.
-
Close the drains and add water until the pressure of
the hydraulic circuit reaches 1 bar.
-
Check that the hydraulic circuit is drained correctly.
-
Close the non-return valves.
-
Check that there are no leaks.
"
The exact filling pressure is determined
according to the installation's manometric head .
figure 31 -
Hydraulic module drain taps
(P)
Manual
drain tap
(P)
Manual
drain tap
(A)
Automatic
drain tap
figure 32 -
Non-return valve
Flap closed
(Normal operating
position)
Flap disengaged
(Filling or drain
position)
Installation and commissioning instructions "1485 - EN"
Heat pump alféa hybrid duo gas
- 36 -
Summary of Contents for WOYG112LHT
Page 51: ... Installation and commissioning instructions 1485 EN 51 Heat pump alféa hybrid duo gas ...
Page 69: ... Installation and commissioning instructions 1485 EN 69 Heat pump alféa hybrid duo gas ...
Page 90: ...Installation and commissioning instructions 1485 EN Heat pump alféa hybrid duo gas 90 ...
Page 91: ...Installation and commissioning instructions 1485 EN 91 Heat pump alféa hybrid duo gas ...