4.7.4 BOILER TESTING

Each boiler is supplied with a control certificate.

The compilation of the certificate of inspection by a Authorized 

Service Center allows you to enjoy the advantages offered

from the insurance formula provided by the second 

manufacturer as specified in the inspection certificate itself.

4.7.5. PRELIMINARY CHECKS

Before testing the boiler it is advisable to check:

- the smoke evacuation duct and the terminal part are

installed according to the instructions: with the boiler on

no escape of products of the

combustion by no gasket;

- the boiler power supply voltage is 230 V - 50 Hz;

- the system is correctly filled with water (pressure at

pressure gauge 1-1.3 bar);

- any pipes interception cocks

of the system are open;

- the network gas corresponds to that of the boiler calibration:

otherwise, carry out the conversion

of the boiler to use the gas available: this operation

must be performed by qualified technical personnel;

- the fuel supply tap is open;

- there are no leaks of combustible gas;

- the general electric switch upstream of the boiler is

inserted;

- the 3 bar safety valve is not blocked;

- there are no water leaks;

- the condensate drain trap, mounted in the boiler,

properly drain the condensate and it is not blocked.

If the boiler is not installed properly to the laws and regulations

in force, notify the manager installation and do not test the

boiler.

4.7.6. MAINTENANCE

Maintenance (and repair) operations must be performed by 

qualified personnel.

The manufacturer advises its customers to contact, for the

maintenance and repair operations, to the network of its own

Authorized Service Centers that are trained to perform

at best the aforementioned operations.

Proper boiler maintenance allows the same to

work in the best conditions, respecting the environment and in

full safety for people, animals and things.

Maintenance operations must be performed at least

once a year.

Before proceeding with any maintenance operation which

involves the replacement of components and / or of

cleaning the inside of the boiler disconnect the appliance from 

the power supply network.

Maintenance operations include control operations and cleaning 

as specified below;

Control operations:

- general check of the integrity of the boiler;

- check the tightness of the gas circuit of the boiler and the

gas supply network to the boiler;

- control of the boiler supply pressure;

- boiler ignition control;

- control of the combustion parameters of the boiler by

smoke analysis;

- integrity check, good state of conservation e

checking the operation of the combustion fan;

AUTO ADJUSTMENT

The message "P0" appears on the display and the card is ready for
set the value of O2 to the minimum power.

“   ” 

Is used to switch between the Power / O2 menu (for the 

cycle time).

“   ” o “   ” 

are used to increase / decrease the value of the O2 

or change the power of the system (if the symbol of flame 

flashes).

By pressing the keys ""   or   "" it will be possible to 

modify the value current RFlame set and vary the O2. Press the      

""   button (for the cycle time) to confirm adjustment to "P0" and 

""   (for the cycle time) to go to second level to be adjusted "P1". 

Proceed with the CO2 calibration following the steps taken for 

adjust the minimum. Press the "" button to confirm and   "" to 

switch to adjustment of the maximum "P2". Adjust the value as 

shown in the table. Confirm with the "" button. Press the 

"MODE" button (without waiting for the cycle time) to finish the 

procedure and memorize the adjustments made.

MENU ADJUSTMENT

The message "P0" and the card appear on the display. ready to 

adjust the CO2 value at minimum power. With this condition:    

"" Is used to switch between the Power / CO2 menu (for the 

cycle time).      Or      are used to increase / decrease the value 

of CO2 or change the power of the system (if the symbol of 

flame flashes). Press the "  " button for the cycle time to activate 

the menu CO2. By pressing the keys       or      it will be possible 

to modify the value RFlame current set and correct CO2. Press 

the    button (for the cycle time) to confirm adjustment to "P0" 

and      (for the cycle time) to go to second level to be adjusted 

"P1". Proceed with the CO2 calibration following the steps taken 

for adjust the minimum. Press the "" button to confirm and     to 

switch to adjustment of the maximum "P2". Adjust the value as 

shown in the table, confirm with the "" button. Press the 

"MODE" button (without waiting for the cycle time) to finish the 

procedure and memorize the adjustments made. It is possible 

to exit the function at any time adjustment by pressing the 

"MODE" button for the cycle time. Finally set P08 at 70% and 

P09 at 80%.

Summary of Contents for HUB RADIATOR PACK CF 3.0

Page 1: ...ATION HUB RADIATOR PACK CF Factory made high efficiency integrated hybrid system patented heat pump with direct exchange refrigerant water to produce DHW heating and air conditioning HUB RADIATOR PACK...

Page 2: ...2...

Page 3: ...3 5 1 4 5 1 5 5 1 6 5 1 7 5 2 6 2 1 6 2 2 6 2 3 6 3 7 3 1 7 3 2 8 3 3 8 3 4 8 3 5 8 3 6 Pump Down 8 3 7 9 4 INSTALLATION OF INDOOR UNITS 10 4 1 Choosing the place of installation 10 4 2 Technical data...

Page 4: ...tructions 27 9 5 General system checks 27 10 START UP 27 10 1 First start up checks 27 10 2 Starting up 27 11 REPAIR COMPONENTS REPLACEMENTS 27 11 1 Refrigerant circuit 27 11 2 Drying and vacuum of th...

Page 5: ...be installed at wall or recessed the indoor unit is supplied complete with all the appropriate ones internal copper exchangers R410A refrigerant gas connections DHW connections air vent valve safety v...

Page 6: ...2 x 0 75 mm 2 x 2 20 A curv D Table 2 Tightening torque Torque Tightening min max N m 1 4 14 18 3 8 33 42 5 8 63 77 Table 3 Refrigerant charge m Max Add refrigerant quantity g m HR 3 0 5 15 5 20 HR 7...

Page 7: ...not compromise the product operation and or personal safety e of assets Make sure that the space at the back of the unit is greater than 30 cm The front must have more than 60 cm of space Ensure that...

Page 8: ...at each tube both the gas side tubes and the liquid between internal group and external group has been connected in the correct way and that all the wiring necessary for the testing have been carried...

Page 9: ...pressure gauge using the refrigerant gas Completely close the liquid valve Turn on the machine in cooling mode When the pressure of the pressure gauge goes from 0 to 0 5 kg 2G cm between 14 2 and 7 1...

Page 10: ...as connection 19 Gas connection R410A 5 8 4 1 CHOICE OF INSTALLATION SITE OF THE HYBRID SYSTEM When determining where to install the internal unit of the system hybrid HUB RADIATOR PACK CF take the fo...

Page 11: ...that the support surface is regular Use the bracket as a template and mark the position of the holes from to achieve x 3 Wilo Yonos Pico 25 18 60 4 5 7 5 4 75 4 6 3 4 3 4 1 2 1 2 230V 1 50Hz 1447 720...

Page 12: ...pipes the weight of which must not burden on the appliance properly insulate the pipes to find the right ones heat losses H Connect a special safety drain in correspondence of the 1 2 female threaded...

Page 13: ...or exclude them safety devices In the event of repeated shutdowns of the boiler it is necessary have the air intake flue gas exhaust ducts checked which may be blocked or inadequate for the disposal o...

Page 14: ...tion that the total path of the fumes from the exit point of the same from the terminal to their outlet from the external perimeter of the balcony including the height of the eventual balustrade of pr...

Page 15: ...temperatura di spegnimento dopo accensione bruciatore 0 20 0 DO NOT MODIFY THIS VALUE P61 Selezione allarme temperatura scarico fumi 20 150 105 P62 Not used P63 Not used P64 Not used P65 Anti legionel...

Page 16: ...0 1 1 DO NOT MODIFY P20 Selection of the minimum value of the DHW 35 50 35 P21 Low temperature zone selection 0 1 0 0 High temperature 1 Low temperature P22 Not used P23 Selection of pump activation t...

Page 17: ...bustion regulation CO2 4 7 3 CHECK AND ADJUSTMENT OF THE GAS VALVE PREMISE The boiler by means of the BEST function is suitable automatically combustion according to the conditions of installation the...

Page 18: ...s specified below Control operations general check of the integrity of the boiler check the tightness of the gas circuit of the boiler and the gas supply network to the boiler control of the boiler su...

Page 19: ...s network and the electricity grid The materials of which the boiler is made are all recyclable Once dismantled the boiler must be disposed of in compliance of the legislation in force in the country...

Page 20: ...o use the boiler only it is necessary to set IC to ON and set DC to EMERGENCY Simultaneously put the CD control in STAND BY by pressing the SUN button Booster terminal board Technical water probe Boos...

Page 21: ...the integration boiler it is necessary to set IC to ON and set DC to INTEGRATION In this way the control unit will decide when the help of the boiler is needed which will work in support of the heat...

Page 22: ...12 3 03 2 91 10 3 45 3 37 3 29 3 20 3 10 2 98 11 3 55 3 46 3 37 3 28 3 18 3 06 12 3 64 3 55 3 45 3 36 3 25 3 13 13 3 75 3 64 3 54 3 44 3 33 3 20 14 3 85 3 74 3 63 3 52 3 41 3 28 15 3 95 3 83 3 72 3 6...

Page 23: ...ting C 30 35 40 45 50 55 1 074 10 2 96 2 59 2 25 1 91 1 59 1 27 HR 3 0 9 3 04 2 67 2 32 1 98 1 65 1 33 8 3 14 2 75 2 39 2 05 1 71 1 39 7 3 23 2 84 2 47 2 12 1 78 1 46 6 3 32 2 92 2 54 2 19 1 84 1 52 5...

Page 24: ...cold water filter 19 Secondary plate heat exchanger 20 Domestic hot water temperature sensor 21 Automatic by pass integrated on plate heat exchanger 22 Motorized 3 way valve S Condensate drain G Gas i...

Page 25: ...an speed x100 TMax operating temperature in heating mode Total expansion vessel capacity 6 5 TECHNICAL FEATURES BOILER HUB RADIATOR PACK CF TECHNICAL FEATURES kW bar bar bar bar l min V Hz A W IP Kg m...

Page 26: ...d mode with the active boiler for DHW production and external booster in active heat pump to produce chilled water up to 4 C per power the hydronic terminals IC ON OFF O I CD 2 0 0 1 2 3 4 5 H m 4 6 8...

Page 27: ...UP Before proceeding with the commissioning of the appliance you need to make sure that the safety conditions and all the provisions listed in this manual has been complied with the fixing to the sup...

Page 28: ...inants that have been must be eliminated introduced to clean the circuit or to effect the operations carried out WARNING Do not inhale the refrigerant vapors coming from burned compressors as it can b...

Page 29: ...as to obtain a temperature of system delivery that increases in a way proportional to decreasing air temperature external To proceed with this function set the value of the parameter ST08 and ST03 at...

Page 30: ...ler Boiler differential boiler Boiler activation delay time boiler SET POINT external air compressor deactivation Compressor activation external air differential PARAMETERS OF ALARMS FUNCTIONS Probe f...

Page 31: ...bled but not active the icon is off ___________________________________________________ On during access to the functions menui ___________________________________________________ Lit if the resistanc...

Page 32: ...ws exit from parameter programming 2 contemporary pressure prolonged keys allows entry into manual defrost ___________________________________________________ Remote terminal Regarding the use of the...

Page 33: ...ure falls below 90 C P1 probe alarm PB1 probe alarm PB2 probe alarm PB3 faulty probe or resistive value out of range faulty probe or resistive value out of range probe alarm PB4 faulty probe or resist...

Page 34: ...al probe 3 Substitution of tract 1 Replacement of the outdoor unit probe 2 Connection cable replacement external probe 3 Substitution of tract 1 Thermostat replacement 2 External booster recharge 3 co...

Page 35: ...int ST21 Set massimo ambiente in chiller ST18 110 230 C F Dec int ST22 Set point ambiente in p d c ST24 ST25 C F dec int ST23 Differenziale ambiente in p d c 0 0 0 25 0 45 C F Dec int ST24 Set minimo...

Page 36: ...pen contact 0 1 CF16 Polarity ID5 0 Active close contact 1 Active open contact 0 1 ventilatore di mandata 13 Allarme termica pompa acqua condensatore 14 Flussostato condensatore CF09 CONFIGURATION ID2...

Page 37: ...sent 1 Continuous operation in ON OFF output 2 Operation on compressor request 3 Continuous output operation 4 20mA 4 Operation on request of the compressor 4 20mA 0 4 CO12 Compressor 0 Enabled 1 OFF...

Page 38: ...6 Minimum defrost alarm 0 Not enabled 1 Enabled 0 1 dF17 Minimum alarm delay when reversing the 4 way valve 0 250 Sec FA09 Maximum fan speed in summer 30 100 FA10 Minimum fan speed temperature pressur...

Page 39: ...utput relay polarity 0 Output without voltage in normal conditions with voltage in the presence of an alarm 1 Output with voltage in normal conditions without voltage in the presence of an alarm 0 1 A...

Page 40: ...CE dei prodotti comporta il controllo costante of production with the aim of guaranteeing the conformity of the appliances with the safety and performance characteristics of the verified samples The...

Page 41: ..._________ Raffrescamento estivo Produzione ACS Riscaldamento Distanza tra unit interna ed esterna max 15 m Dislivello tra unit interna ed esterna max 5 m Le tubazioni delle linee frigorifere 1 4 3 8 p...

Page 42: ..._________________________________________________________ Attenzione la mancata effettuazione del primo avviamento per cause non dipendenti dall unit comporter una seconda visita la quale sar a voi di...

Page 43: ..._____________ ___________ ________________ BOOSTER POSIZIONATO A TERRA A MURO A FINESTRA SU STAFFE ANTIVIBRANTI MENSOLE A TETTO ALTRO SU BASI A SOSPENSIONE A RINGHIERA INSTALLAZIONE CON PONTEGGIO SI N...

Page 44: ...AICO SPENTO FUNZIONAMENTO IN POMPA DI CALORE BOOSTER 1 TEMPERATURA DI EVAPORAZIONE U E C Pb3 _______ TEMPERATURA ACQUA TECNICA C Pb1 _______ NB TEMPERTATURA DI INIZIO CONDENSAZIONE C _______ Attendere...

Page 45: ...ence must be made to the natural or legal person who has purchased the Product regardless of whether the seller is A2B ACCORRONI E G or other person marketing branded products A2B ACCORRONI E G This w...

Page 46: ...rroni mediante ogni opportuna operazione di trattamento manuale ed informatico per finalit funzionali all adempimento degli obblighi derivanti dal contratto di fornitura di beni servizi da parte di Ac...

Page 47: ...provisions of the law on the subject of deduction for the energy requalification costs of the existing building heritage the A2B Accorroni E G Ltd DECLARES that the product complies with the European...

Page 48: ...corroni E G s r l Via d Ancona 37 60027 Osimo An Tel 071 723991 web site www accorroni it e mail a2b accorroni it A2B Accorroni E G S r l reserve the right to make changes without prior notice TECHNIC...

Reviews: