13
WARNING! all electrical connections must be
performed by qualified personnel and the electrical system must
comply with all applicable regulations
L) Proceed with the refrigeration connections following all the
instructions given in section 2.3 of this manual. In
shape the pipes avoid any type of squashing and
make sure that each portion of the pipe is perfectly
thermally insulated from beginning to end.
WARNING! complies with all applicable regulations.
All refrigeration connections must be carried out by
qualified personnel with F-GAS certification
(Presidential Decree January 27, 2012, No. 43)
M) Once all the connections have been made, request the
internal unit
with the special cover cabinet that must be placed first
from top to bottom on the wall mounting bracket and then done
rotate towards the wall until hooking on the appropriate pins a
disappearance, placed on the lower fixing plate.
4.5 FLUE / AIR DISCHARGE OPENING SYSTEM
In the internal unit of the HUB RADIATOR PACK hybrid system
CF is a highly efficient condensing boiler
Modulating.
Regarding the discharge of fumes into the atmosphere and the
systems of
air intake / fume exhaust comply with laws and regulations
in force, which here are intended as fully transcribed.
Safety devices are installed on the boiler for the boiler
control of the evacuation of combustion products.
exhaust fumes the devices put the boiler in safety and on the
LCD display shows the flashing code E14. It is absolutely
forbidden to tamper with and / or exclude them safety devices.
In the event of repeated shutdowns of the boiler it is necessary
have the air intake / flue gas exhaust ducts checked, which
may be blocked or inadequate for the disposal of fumes in the
atmosphere. For the air intake / flue gas exhaust, the following
must be used ducts and specific systems for original condensing
boilers, resistant to the attack of condensation acids.
The exhaust pipes must be installed with one slope towards the
boiler to guarantee the reflux of the boiler condenses towards
the combustion chamber that is built for collect and discharge
the condensate.
If this is not possible it is necessary to install, in condensation
stagnation points, systems capable of collect and convey the
condensate to the exhaust system of the condensation.
Condensation stagnation points in the system must be avoided
evacuation of combustion products, with the exception of of
liquid of the eventual siphon connected to the system of
evacuation of combustion products.
The manufacturer declines all responsibility for damage caused
to following errors in installation, use, transformation
of the appliance or failure to comply with the instructions
provided by the manufacturer or the current installation
regulations concerning the material in question.
In case of malfunction of the intake system a
Terminal
Gas line connection
Liquid line connection
R410A
Liquid tap
Gas line connection
Gas line connection
External booster
Internal unit
For wall positioning of the exhaust terminals of the boiler, in the
cases prescribed by DPR n.551 dated 12/29/99, follow at the
distances indicated in the table and in the figure below.
Air aspiration Fume exhaust Condensate