Section 10
Establishing connection and verifying the
LON communication
About this chapter
This chapter explains how to set up LON communication and how to verify that
LON communication is up and running.
10.1
Communication via the rear ports
10.1.1
LON communication
LON communication is normally used in substation automation systems. Optical
fiber is used within the substation as the physical communication link.
The test can only be carried out when the whole communication system is installed.
Thus, the test is a system test and is not dealt with here.
The communication protocol Local Optical Network (LON) is available for 670
IED series as an option.
1MRK 504 088-UEN C
Section 10
Establishing connection and verifying the LON communication
93
Installation and commissioning manual
Summary of Contents for RELION RET670
Page 1: ...Relion 670 series Transformer protection RET670 Installation and commissioning manual...
Page 2: ......
Page 16: ...10...
Page 24: ...18...
Page 26: ...20...
Page 28: ...22...
Page 82: ...76...
Page 88: ...82...
Page 94: ...88...
Page 104: ...98...
Page 110: ...104...
Page 210: ...204...
Page 230: ...224...
Page 239: ...233...